 Wed Jan 21, 2009
Sultan Minerals Releases Updated NI 43-101 Tungsten Resource

 Sultan Minerals Inc. (SUL -- TSX Venture) ("Sultan" or the "Company") is pleased to announce that it has now received updated resource calculations for the Tungsten Zones on its Jersey-Emerald Property in the Kootenay District of British Columbia. The updated resource estimate shows a measured plus indicated resource of 2,719,000 tons averaging 0.358% WO3, and an additional inferred resource of 2,320,000 tons averaging 0.341% WO3 at a 0.15% WO<sub>3</sub> cutoff. The mineralization remains open along strike.

Resource calculations were prepared by Giroux Consultants Ltd. of Vancouver, BC and the resulting National Instrument 43-101 Technical Report was co-authored by independent geological consultants Gary Giroux, P.Eng., of Giroux Consultants Ltd. and Perry Grunenberg, P.Geo. of PBG Geoscience from Kamloops, BC.

In determining the updated resource, separate tungsten resource estimations were produced for the Emerald Mine Area and the recently discovered East Emerald Zone. The weighted averages for these two zones were then combined with the previously reported 2006 resources. As shown in the following table, the combined estimate shows a measured plus indicated resource of 2,719,000 tons averaging 0.358% WO3, and an additional inferred resource of 2,320,000 tons averaging 0.341% WO3, using a cut-off grade of 0.15% WO3.

COMBINED 2006-2008 TOTAL WO3 RESOURCE SUMMARY

Year

Deposit

Classification

Cutoff

Tons>Cutoff

WO3
%

Pounds of
WO3

2006

Dodger,
East Dodger
and Invincible

Measured

0.15

1,200,000

0.379

9,096,000

Indicated

0.15

1,310,000

0.365

9,563,000

Measured + Indicated

0.15

2,510,000

0.372

18,674,000

Inferred

0.15

1,210,000

0.397

9,607,000

2008

Emerald and East Emerald

Indicated

0.15

209,000

0.188

786,000

Inferred

0.15

1,110,000

0.285

6,327,000

2006 &
2008

Combined

Measured + Indicated

0.15

2,719,000

0.358

19,460,000

Inferred

0.15

2,320,000

0.341

15,934,000


In computing the updated resource estimates geologic domain three dimensional solids were constructed to constrain three mineralized areas: the Emerald Mine Area, East Emerald -- Upper and East Emerald -- Lower zones. Separate resource estimations were produced for tungsten in the Emerald Mine Area and East Emerald Zones based on 633 diamond drill holes totalling 121,248.6 ft of core. Of these 242 drill holes had intersections within the mineralized zones for a total of 42,303 ft of mineralized core.

Within the high grade Emerald mine, tungsten assays were capped at 8.0 % WO3, while in the low grade East Emerald zones tungsten assays were capped at 1.1 % WO3.

The Company's consultants have suggested that 0.15% WO3 might be a realistic cutoff grade for an open pit operation while a cutoff of 0.24 % WO3 might be realistic for an underground mining operation in this location at current tungsten prices, which is compatible with the 2006 resource estimate. The following tables set out the measured plus indicated resource at cutoff grades for WO3 ranging from 0.02% to 0.30%.

EMERALD AND EAST EMERALD ZONES
INDICATED RESOURCE WITHIN TOTAL DILUTED BLOCKS

WO3 Cutoff
(%)

Tons > Cutoff
(tons)

Grade > Cutoff
WO3 %

Pounds of
WO3

0.02

1,754,000

0.081

2,841,480

0.04

1,334,000

0.097

2,587,960

0.06

997,000

0.114

2,273,160

0.08

726,000

0.130

1,887,600

0.10

487,000

0.150

1,461,000

0.12

350,000

0.166

1,162,000

0.14

245,000

0.182

891,800

0.15

209,000

0.188

785,840

0.16

157,000

0.200

628,000

0.18

99,000

0.217

429,660

0.20

59,000

0.237

279,660

0.22

43,000

0.248

213,280

0.24

12,000

0.291

69,840

0.26

9,000

0.308

55,440

0.28

6,000

0.323

38,760

0.30

3,000

0.355

21,300




EMERALD AND EAST EMERALD ZONES
INFERRED RESOURCE WITHIN TOTAL DILUTED BLOCKS

WO3 Cutoff
(%)

Tons> Cutoff
(tons)

Grade > Cutoff
WO3 %

Pounds of
WO3

0.02

8,640,000

0.093

16,070,400

0.04

6,460,000

0.115

14,858,000

0.06

4,590,000

0.142

13,035,600

0.08

3,320,000

0.169

11,221,600

0.10

2,490,000

0.196

9,760,800

0.12

1,840,000

0.226

8,316,800

0.14

1,370,000

0.259

7,096,600

0.15

1,110,000

0.285

6,327,000

0.16

930,000

0.311

5,784,600

0.18

760,000

0.343

5,213,600

0.20

600,000

0.383

4,596,000

0.22

550,000

0.399

4,389,000

0.24

470,000

0.429

4,032,600

0.26

410,000

0.455

3,731,000

0.28

370,000

0.476

3,522,400

0.30

340,000

0.492

3,345,600



Within the Emerald Mine, tungsten resource estimations were determined only for the un-mined mineralization in the drilled out portions of the deposit. In order to account for underground mining the proportion of underground voids within each resource block was determined and this amount of material was subtracted from the tonnage calculated for that block.


The report makes a number of recommendations that can be summarized as follows:

1) An additional 5,000 metres of diamond drilling be completed to fully define the Emerald and East Emerald tungsten zones.

2) A total of 20 excavator trenches be put in to test the East Emerald zone and its projected extension to the north and south.

3) The Invincible mine workings should be dewatered and the access portals stabilized to provide access for underground drill testing of the East Emerald Tungsten zone and the Invincible workings.

4) The East Dodger resource estimate should be updated to include the recent drilling.

5) The 2007 economic scoping study should be updated and should include:
  1. Preparation of a mine plan;
  2. Design and costing of surface facilities;
  3. Continuing implementation of environmental studies;
  4. Review of ore transport options;
  5. Review of tailings disposal options;
  6. Review wastewater disposal alternatives; and
  7. Review historic metallurgy and conduct further metallurgical testing.

The combined total cost to complete the recommended work is estimated at $1,358,500.

The Company is very pleased with the results of this updated resource estimate. The study shows a significant tungsten resource on the property with potential for expansion both within the historically mined areas and within the surrounding terrain.

Mr. Perry Grunenberg, P.Geo., of PBG Geoscience from Kamloops, BC, is Sultan's project supervisor and "Qualified Person" as defined by NI 43-101, "Standards of Disclosure for Mineral Projects". Mr. Ed Lawrence, P.Eng, former Manager of the Jersey and Emerald Mines under Placer-Dome, oversees all on-going diamond drilling programs for Sultan.

For further information on the Sultan's projects, visit www.sultanminerals.com.

Arthur G. Troup, President and CEO

For further information, please contact:
Marc Lee, Investor & Corporate Communications
Tel: (604) 687-4622 Fax: (604) 687-4212 Toll Free: 1-888-267-1400
Email: mlee@sultanminerals.com or info@sultanminerals.com

The TSX Venture Exchange has not reviewed and does not accept responsibility for the adequacy or accuracy of the contents of this News Release. This release was prepared by Sultan management and no regulatory authority has approved or disapproved the information contained herein. This news release includes certain statements that may be deemed "forward-looking statements." All statements in this release, other than statements of historical facts, that address future production, reserve potential, exploration drilling, exploitation activities and events or developments that the Company expects are forward-looking statements. Although the Company believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include market prices, exploitation and exploration successes, and continued availability of capital and financing, and general economic, market or business conditions. Investors are cautioned that any such statements are not guarantees of future performance and those actual results or developments may differ materially from those projected in the forward-looking statements. For more information on the Company, investors should review the Company's filings that are available at www.sedar.com or the Company's website at www.sultanminerals.com.


Click to Enlarge
 
 

You can view the Next News Releases item: Tue Feb 17, 2009, Sultan Minerals Identifies Potential New Tungsten And Zinc Deposits At Jersey-Emerald, BC

You can view the Previous News Releases item: Thu Jan 8, 2009, Sultan Minerals - Focussing On Metals Unaffected By The Commodities Crunch

You can return to the main News Releases page, or press the Back button on your browser.

Suite 2000 - 1066 West Hastings Street, Vancouver, British Columbia, Canada V6E 3X2   •  Tel 604-628-0519   •  Fax 604-628-0446